Manhattan Community District 5 is in sub-cycle B.
Cycle 2 inspection window: Jan 1 to Dec 31, 2025.
The Cycle 2 window ran Jan 1 to Dec 31, 2025. The next window (Cycle 3) opens Jan 1, 2029.
Cycle 3: Jan 1 to Dec 31, 2029.
Local Law 152 requires a gas piping inspection at least once every four years for all buildings except one- and two-family homes and Occupancy Group R-3 buildings. Sub-cycle B covers community districts 2, 5, 7, 13, 18 in each borough. Check your building’s district with the DOB address search if you’re unsure.
The process
What has to happen.
- A Licensed Master Plumber (or a qualified individual working for one) does the inspection.
- You get the inspection report within 30 days.
- The certification is filed with DOB within 60 days of the inspection.
- Corrections, if needed, are certified within 120 days (180 days if more time was requested).
- One 180-day extension of the inspection due date is available online.
- Late filing can bring a $5,000 civil penalty.
Missed the deadline, or got a violation or penalty for gas piping? That’s where we come in. We handle the DOB filings, violation removal and hearings. We don’t perform the inspection itself.
Call (929) 367-0962Other districts
More in Manhattan.
- District 1
- District 2
- District 3
- District 4
- District 6
- District 7
- District 8
- District 9
- District 10
- District 11
- District 12
Use the lookup tool or see every borough.
Source
Official source.
Schedule as published by DOB, last reviewed November 15, 2026. Confirm with DOB; this isn’t legal advice.